Mill 2 liner reline: request to defer
1 Decision sought
Defer the Mill 2 reline planned for 14 October.
2 Background
Below 30 mm a liner must be replaced. The high-grade campaign runs to 24 October.
3 Evidence
41 mm now, wearing 0.8 mm a day. Bolt 14 tension is down 6%; its sensor was calibrated on 2 October.
Relining takes 36 hours and would stop the high-grade campaign.
Relining now: about $1.9 million of lost production. An unplanned failure: about $6 million.
At 14 days the liner would be under 30 mm. We would stop that job.
4 Options
5 Decision
C, within delegation 2.1.